September 2020 Model making for the Sculpture Garden.
Although we worked on scaffolding and brickwork on level three and cast another 10 Crenels, my main achievement was making a start on our...
August 2020 Trying to waterproof level one.
We concreted the battlements around the level one dining room and painted with waterproofing. Hopefully, we will now be able to...
July 2020 Allsorts.
A few different things happened this month. Level three battlements were worked on; three more crenels were mosaiced; Francis removed the...
Two days in June 2020!
Not a lot to talk about for rainy June. We managed a day and a half this whole month. We almost got the central room on level three...
2020 May First Glazing on Build.
We installed five windows in the stairwell which comprised of glass bricks.
2020 April Stairwell and central studio.
Only managed to work nine days on the Build this month. Worked on getting these two rooms to height.
2020 March Windows and doorway in.
It always feels like a lot is happening when you brick over window and door arches.
2020 February Bricking Level Three
One month after the slab was laid we started bricking my studio. Five mixes and we up to putting in the window shapes.
2020 January CONCRETE DAY!
The final floor slab on the Castle laid this month. To make the maximum use of the concrete pump, we also concreted six areas in the...
27 days Finishing Ballroom.
The Sphere Room now dubbed the "Ballroom" was lined with over 11,000 small Hebel blocks. This room is now a perfect sphere and the sound...